New Life Ministries Relocation/Renovation Needs

DESCRIPTION
Estimated
Cost
Subtotal
Expenses Already Incured
Architectural & Engineering
$21,267.46
Permits
$600
Framing
$12,200
$34,067.46
Funds Necessary to Gain Occupancy
Permits
$900.00
Plumbing
$9,200
HVAC
$16,500
Electrical Materials
$15,000
Electrical Labor
$8,800
Drop Ceiling
$6,800
Floor Leveling
$4,000
Insulation
$3,800
Sheet Rock
$22,500
Electrical Light Fixtures
$12,703
Low Voltage Materials
$500
Fire Sprinklers
$9,275
Fire Alarm System (Waiting on bid)
$5,000
Doors & Trim
$16,300
Door & Bathroom hardware
$2,500
$133,778
SUBTOTAL for Basic Construction for Occupancy
$167,845.46
LESS Funds Raised to Date
- $100,161.05
FUNDS NEEDED FOR OCCUPANCY
$67,684.41
Funds AFTER Occupancy
(these items will be completed as funds are available AFTER occupancy)
Carpet
$19,200
Sound & Video
$10,000
Paint & Floor Finish
$12,500
Cabinets & Reception
$19,000
Window shades
$5,000
Decorating
$10,000
$75,700